Efficient Program Management Drives $267 Million Goose Creek CISD Makeover: Part II

By J.P. Grom

The IMPACT Early College High School corridor is active with students between classes, and makerspaces to the left encourage collaborative learning.
The IMPACT Early College High School corridor is active with students between classes, and makerspaces to the left encourage collaborative learning.

BAYTOWN, Texas — Headquartered in Baytown is one of the fastest growing school districts in Texas — the Goose Creek Consolidated Independent School District (GCCISD). Driven by multi-billion dollar expansions at petrochemical companies such as ExxonMobil, Chevron and ConocoPhillips, this property-wealthy district is projecting more than 4,500 new students over the next decade, according to a demographic study. To accommodate this growth, forward-thinking area residents, business and industry representatives, community leaders and district personnel passed a $267 million bond in May 2013, following many months of work.

The bond program, one of the largest in Texas, touches every facility within the district’s inventory. It adds several new facilities, including three new elementary schools with room for 850 students each, a new transportation center, a data technology center and an agricultural science building. The bond package also includes additions to four facilities, renovation of STEM labs in five schools and security upgrades. In addition, the bond package will also enable GCCISD to accomplish its goal of retiring $52 million in deferred maintenance.

To manage such a large and complex program, GCCISD in January 2014 selected Houston-headquartered Lockwood, Andrews & Newnam Inc. (LAN) as the program manager. Complicating the challenge was the fact that LAN was hired late in the program after some of the major projects were already underway. Facing possible budget and schedule concerns, the district tasked LAN with maintaining control by managing every aspect from the beginning to the end.

In the first part of this article, we discussed a multi-step process that emphasized three critical components — budget, schedule and quality — during each step. Here, we will examine the program’s unique challenges.

Program Challenges

The size and scale of the program provided a number of challenges. One of them was opening the three new elementary schools on time. To accomplish this objective, the project team looked for ways to accelerate the construction schedule by insisting that all the major decision makers work in-house in the district’s offices. No decision was allowed to linger longer than 24 hours. If the schedule didn’t allow full recovery to accommodate all owner-provided activities (move in, cleaning, floor waxing, etc.), options were considered that deferred work without impeding the arrival of the kids until later. While it was not ideal, it addressed the reality of school construction: “the kids are coming.”

At the Alamo Elementary School a colorful computer-based learning center is housed within each traditional learning center.Photo Credit (all): LAN
At the Alamo Elementary School a colorful computer-based learning center is housed within each traditional learning center.
Photo Credit (all): LAN

Another major challenge was inadequate scope definition for almost every major project in the program. For example, while the district wanted a new technology center, details such as square footage, type of construction and the equipment needed for the building weren’t available. The only information the project team had was the total amount of money available for the program. Working with the owner and other stakeholders, the project team forensically reconstructed the bond program based on the funds available to accomplish the program’s broad objectives. By methodically working through the details of the program, LAN scoped each project in such a way that it would not only satisfy the district’s expectations but also be completed on budget and ahead of schedule.

Additionally, GCCISD’s condition assessment was done a couple of years prior to the bond elections. As a result, the information in the facilities condition assessment was time-dated. Through site inspection and collaboration with multiple stakeholders, LAN’s team validated or disputed the work requirements proposed in the facility condition assessment prepared by the previous firm. This work resulted in several million dollars savings in scope management that allowed the district to achieve additional project scope elsewhere in the program.

Finally, the district distributed the work to multiple architecture and engineering firms. As such, as many as 20 design and contracting firms worked on different facilities during the course of the program. This required managing firms with different cultures and operational methods. Through consistent verbal and written communications, LAN provided updates on design and construction schedules, costs, requested changes, and other areas of vital importance to the district’s interest. Status reports, open issues lists, and memorandums were transmitted on a regular basis through email and phone calls. This documentation, along with other project records, were made available to the district at any time. Meetings were scheduled on a regular basis to review open issues and provide status reports. Additionally, district representatives were invited to participate in all meetings that they deemed appropriate.

Conclusion

Thanks to this highly efficient process, the Goose Creek bond program is now running almost a year ahead of schedule. The three elementary schools were completed in 2014. The mechanical, electrical and plumbing upgrades, as well as safety and security improvements were completed last year. The transportation center just broke ground and bidding is about to start on the technology building. Within the next three months, all major projects will be awarded to contractors. The GCCISD program is an excellent example of how a large and complex capital improvement program can be implemented cost-effectively while satisfying the community’s expectations at the same time.

J.P. Grom, AIA, is a vice president and team leader at Lockwood, Andrews & Newnam, Inc., a planning, engineering and program management firm. He can be reached at JPGrom@lan-inc.com.