Texas School District Bond Program Projects Ramp Up
Several school projects in the Goose Creek Consolidated Independent School District’s (CISD) $335 million bond program are progressing rapidly, even amidst the current coronavirus pandemic.
Several school projects in the Goose Creek Consolidated Independent School District’s (CISD) $335 million bond program are progressing rapidly, even amidst the current coronavirus pandemic.
The recently completed $28 million Menchaca Elementary School for the Austin Independent School District is a design-build project that has replaced an existing campus in a growing area of south Austin.
In early March, a “Foundation Celebration” was held in Denton, Texas for the new Denton High School.
The Cleveland Independent School District in Texas recently selected Lockwood, Andrews & Newman, Inc. as program manager for its nearly $200 million bond program for the construction of two new elementary schools and middle school, plus more.
On November 21, representatives from VLK Architects attended the dedication ceremony for Lamar Consolidated Independent School District’s (LCISD) newest elementary campus, Judge Thomas R. Culver Elementary School.
In mid-October, a ribbon-cutting ceremony was held commemorating the opening of the newly renovated Spring Valley Region 10 Education Service Center in Richardson.
On September 17, a groundbreaking ceremony was held for the reconstruction of Socorro High School in El Paso.
On September 5, a ribbon-cutting ceremony was held to commemorate the opening of T.W. Ogg Elementary School in Clute, Texas.
On September 5, a rededication ceremony was held to commemorate the reopening of League City Elementary School in League, Texas.
The Goose Creek Consolidated Independent School District (GCCISD) has selected Lockwood, Andrews & Newnam, Inc. (LAN) as the program manager for its $335 million bond program.